STATUS OF BHARATNET AS ON 16.07.2017

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,39,285 Kms (1,06,508 GPs)

2.

Optical Fibre laid

2,20,959 Kms (100,253 GPs)

3.

Tenders Finalized

3324 Blocks / 1,24,412 GPs

4.

Work Started*

3225 Blocks / 1,20,858 GPs

5.

Current Weekly performance of Optical Fibre laying

820Kms

6.

Current Weekly performance of OFC Pipe laying

796 Kms

7.

Optical Fibre Cable Delivered on site 

2,56,028 Kms

8.

GPON Integrated & Tested (Lit)

24,154 GPs

* does not include the data of Andhra Pradesh 